Breda II BD150
Project description
Construction of 3 containers with switchboards and internal installations. They constitute a replacement control unit for control at transformer stations at the client's site in the Netherlands. Containers prepared according to customer guidelines by using protective coatings, using appropriate class doors and anti-panic functions, internal insulation and an air conditioning unit. There are Harting connectors on one of the walls. Each container contains switchboards and installations between the switchboards and Harting connectors on the wall.
Scope of work
On the "Breda II BD150" project, our company was responsible for:
- purchase and delivery of appropriate materials and components necessary for construction
- construction of switchboards
- mechanical inspection of switchboards
- detailed as-built measurements and verification of connections
- FAT tests
Movie